ADX targeting more gas below, more barrels above

ADX has already flowed HOCH-1 at up to 548 BOEPD, now it's going deeper while chasing another 100 BOEPD from its Vienna Basin fields...

ADX Energy (ASX:ADX) is lining up the next phase of testing at its HOCH-1 gas discovery while using the same workover campaign to target a production boost from its Vienna Basin fields.

The combined program starts on 19 October and is designed to do two things at once.

Test another deeper Hall Channel gas reservoir at HOCH-1, and add around 100 BOEPD from ADX’s existing Austrian production base.

Figure 1: ADX exploration licences and producing fields in Austria.

HOCH-1 has already shown it can flow

Phase 1 testing delivered a stable 2.7 MMCFPD from the first zone, equivalent to around 450 BOEPD.

A later commingled test across multiple zones increased that to 3.15 MMCFPD, or around 548 BOEPD.

Pressure and flow data also confirmed additional gas contribution from three further zones.

That gives ADX a strong platform heading into Phase 2.

The deeper Hall Channel is next

The next test will focus on at least one deeper Hall Channel reservoir, with Zone 6 the initial target.

The workover rig will remove the existing completion, drill out the cement plug and recomplete the well before the deeper zone is perforated.

ADX says post-drill seismic mapping suggests the Hall Channel sands may extend laterally for at least 2.5km to the southeast.

Figure 2: Shows the post drill mapping and the well correlations that indicate a large extension of the stratigraphic trap (at least 2.5 km to the SE).

Vienna could add another 100 BOEPD

At the same time, ADX will run production enhancement work across its Vienna Basin fields.

The program includes new gas-zone perforations, a pump replacement and a new production interval with sand-control completion.

Combined, the work is expected to add ~100 BOEPD.

That would represent roughly a 40% increase in ADX’s Austrian production.

One rig, two catalysts

The advantage is efficiency.

ADX is combining the HOCH-1 testing and Vienna production work into a single workover campaign, reducing duplication while advancing both growth and cash flow.

Phase 2 HOCH-1 testing is expected to begin on 15 December.

Figure 3: MB well services rig contracted for the ADX’ Vienna Basin well work program and HOCH-1 Phase 2 testing program.

What comes next

First comes the Vienna production work.

Then HOCH-1 gets reopened for deeper testing.

The near-term question is whether ADX can turn the next Hall Channel zone into another commercial flow result while lifting baseline production at the same time.