Core Energy mobilises rig to Barking Gecko as maiden Nova JV drilling nears | ASX: CR3

Core Energy Minerals (ASX: CR3) has mobilised its geological team and drilling contractor to the Barking Gecko uranium prospect in Namibia. Diamond and reverse circulation (RC) drilling is expected to begin imminently, marking the company’s maiden drilling campaign at the Nova Joint Venture.

Mobilisation began on 2 November 2026. CR3’s in-country team is on the ground handling site establishment, safety inductions, drill-pad preparation and rig set-up. The program will be supervised by the company’s geological team.

A 24-hole program, starting with four priority holes

The full Barking Gecko program comprises 24 drillholes for approximately 5,280m, split into two phases:

  • Phase 01: 12 holes for approximately 2,640m. It begins with four priority holes totalling about 880m, made up of roughly 290m of RC pre-collars followed by about 590m of diamond tails.
  • Second stage: a further 12 holes for about 2,640m, scheduled for 2027.

After the priority section, CR3 plans step-out drill traverses to complete Phase 01.

The two drilling methods do different jobs. RC drilling is a faster, more efficient way to test mineralised trends and potential extensions along strike and at depth. Diamond drilling produces oriented core, which allows detailed geological and structural logging, density measurements and sampling. The company says the program will test the interpreted continuation of mineralised leucogranite sheets, as well as priority structural positions identified from historical drilling, geological information and geophysical data. Drilling permits are already in place.

What historical drilling found

Barking Gecko is a basement-hosted uranium system on Exploration Licence EPL3669, defined by 82 historical RC and diamond drillholes. That drilling, previously reported by Deep Yellow, intersected multiple zones of uranium mineralisation hosted within stacked leucogranite sheets. Significant historical intersections include:

  • 45m @ 222ppm eU3O8 from 120m (TN253RC)
  • 21m @ 886ppm eU3O8 from 199m (TN258RC)
  • 27m @ 251ppm eU3O8 from 234m (TN258RC)

Grades reported as eU3O8 are equivalent uranium values derived from downhole gamma logging, not laboratory assays. The intercepts are downhole lengths, and true widths have not been established.

According to CR3, geological modelling indicates a consistent series of broadly parallel mineralised sheets extending over several hundred metres of strike and depth. The company says high-grade mineralisation remains open at depth and along strike, and that the combination of multiple sheets, substantial historical intercepts and untested extensions supports the potential for a materially significant uranium system.

CR3 has also published an interpreted mineralisation footprint to illustrate its drill targeting. The company notes this interpretation is not a Mineral Resource estimate under the JORC (2012) Code and should not be treated as an estimate of resources or reserves.

Location and the Nova JV

Barking Gecko sits adjacent to Bannerman Energy’s Etango Uranium Project, which CR3 describes as world-class, in Namibia’s Erongo Region. The Erongo also hosts operations and projects including Husab, Rössing, Tumas and Langer Heinrich.

The Nova JV comprises granted licences EPL3669 (Tumas North) and EPL3670 (Chungochoab). Under its staged earn-in, CR3 can earn an initial 25% interest by spending A$2.0 million within 18 months, and a further 26% (51% in total) by spending another A$3.0 million over the following 24 months. CR3 is manager of the joint venture during the earn-in. The Nova tenements adjoin CR3’s wholly owned Gemsbok and Oryx uranium licences.

Company comment

Managing Director Tony Greenaway said: “Engaging a drilling contractor and locking in mobilisation for the first week of November is a major step for Core Energy. Within weeks of executing the Nova earn-in agreement, we are about to put drill rigs on the ground at Barking Gecko. Our team has identified immediate drill targets in a prospect with thick, high-grade historic intersections that remain open at depth and along strike.”

What’s next

CR3 will begin with the priority section of four RC/diamond holes, followed by step-out traverses. As each hole is drilled, the team will carry out geological and structural logging, downhole surveying and systematic sampling.

Downhole gamma results, reported as %eU3O8, will give the company an early read and support timely reporting. Samples will also be sent to ALS Laboratories, and material results will be released after quality assurance and interpretation.

For investors, the key question now moves from the historical record to new data: whether CR3’s own drilling extends the mineralisation the earlier holes left open.