Gold Hydrogen turns up the pressure

Australia’s helium comeback just took another step forward, as Gold Hydrogen's Ramsay flow test strengthens the path to commercial production.

Gold Hydrogen has taken another major step towards becoming Australia’s next domestic helium producer after successfully flowing, purifying and bottling helium from its Ramsay 1 well.

It’s the first time helium has been concentrated and bottled in Australia since the Darwin helium plant closed in 2023, marking a significant milestone for both the company and the country’s critical gas supply.

A world-class reservoir

The Ramsay 1 flow test delivered more than just helium.

Testing confirmed an exceptionally productive reservoir capable of raw gas flow rates of up to 128 Mscf/day and helium flow rates of up to 24.3 Mscf/day from the Kulpara Dolomite.

The reservoir recorded a productivity index of up to 34 bbl/day/psi, well above the sub-2 bbl/day/psi typically seen in commercial low-permeability reservoirs, indicating well performance was limited by pump capacity rather than the reservoir itself.

High-grade helium, proven at surface

Onsite processing achieved helium purity of up to 30%, stabilising around 19%, while raw helium concentrations reached 13% and were still climbing when testing concluded.

Those grades compare favourably with many commercial helium developments globally, where projects can operate with helium concentrations as low as 1%.

The company also successfully separated, purified and bottled helium onsite using Quantum Technology Corporation’s purification system, validating another key piece of the commercial development puzzle.

Table 1: Ramsay 1 measured and modelled flow rates.

Commercial pathway becoming clearer

The results also strengthen the independent commercial development pathway outlined by Worley, which concluded a helium project could potentially be viable with as few as two production wells.

Gold Hydrogen now plans to accelerate Front-End Engineering Design (FEED) studies while progressing towards a maiden Contingent Resource.

Importantly, the Ramsay project follows a dissolved-gas-in-water development model already operating successfully overseas, including in Japan.

What’s next

The flow testing campaign now shifts to Ramsay 2 before moving to Ramsay 3, with both wells set to evaluate additional helium-bearing reservoirs and prioritise testing of the project’s natural hydrogen zones.

With Australia currently importing all of its helium and global supply remaining tight, Gold Hydrogen believes Ramsay could play a key role in restoring domestic helium production.